Although the Crescent Dunes solar project cost over a billion dollars, received a federal loan guarantee under the Obama administration, filed for bankruptcy, and sold for 7 million dollars, the claim is mostly false because official projections and settlements indicate the ultimate taxpayer loss was significantly lower than 508 million dollars.
A billion-dollar Nevada solar plant backed by the Obama administration went bankrupt twice, was sold for 7 million dollars, and resulted in a 508 million dollar taxpayer loss.

Why Did Crescent Dunes Fail? $1B Solar Plant Sold for $7M
Source: pagetwentyone.com
Key Evidence
The Crescent Dunes solar project cost over 1 billion dollars to build and received a 737 million dollar federal loan guarantee under the Obama administration.
The operating company filed for bankruptcy twice and was sold for 7 million dollars following severe molten salt tank leaks and the loss of its power purchase agreement.
Initial federal loss projections and recovery agreements placed estimated taxpayer exposure well below the 508 million dollar figure cited in the claim.
What the Evidence Shows
The Crescent Dunes Solar Energy Project near Tonopah, Nevada, was a pioneering concentrated solar power plant that cost over 1 billion dollars to build and secured a 737 million dollar loan guarantee in 2011 from the Department of Energy under the Obama administration. The facility experienced severe technical problems, including molten salt tank leaks, prolonged operational shutdowns, and the subsequent loss of its primary power purchase agreement with NV Energy.pvtimes.compvtimes.comDoe Tonopah Solar Come to an AgreementOperational Collapse & Second Bankruptcy: Plagued by technical failures, molten salt tank leaks, and the loss of its primary power purchase agreement with NV Energy These complications culminated in multiple financial collapses for the operating company, Tonopah Solar Energy.
apnews.comapnews.comGeneral News Dbf245cbfa0192d3a16b3860108d899eThe Announcement: In July 2020, when the project’s operating company (Tonopah Solar Energy) first filed for Chapter 11 bankruptcy, the U.S. Department of Energy announced a bankruptcy settlement agreement to recover $200 million in taxpayer funds+3 more
The project entered Chapter 11 bankruptcy protection initially in July 2020, leading to a settlement agreement by the Department of Energy designed to recover a substantial portion of the taxpayer funds involved.swfinstitute.orgswfinstitute.orgUs Taxpayer Backed Tonopah Solar Energy Files for Bankruptcy ProtectionAt that time, the DOE reached a settlement to recover a portion of the funds, with initial projected government losses on the loan guarantee estimated around $225 million to $232 million Initial government loss projections during the first bankruptcy hovered between roughly 225 million and 232 million dollars rather than the 508 million dollars asserted in the claim. Following ongoing financial struggles, the facility filed for a second Chapter 11 bankruptcy in January 2026 and was subsequently sold through a structured asset sale process to Tonopah Energy Center LLC for 7 million dollars. While the project suffered major financial distress, high-profile operational failures, and a multi-million-dollar sale price, the specific 508 million dollar taxpayer loss figure lacks support in the official financial record and exceeds preliminary federal loss estimates.
pagetwentyone.compagetwentyone.comWhy Did Crescent Dunes Fail? $1B Solar Plant Sold for $7MThe claim concerning the Crescent Dunes solar plant, the $507M–$508M taxpayer loss, the DOE loan guarantee, and its bankruptcies is grounded in factual events, though the total financial impact involves a mix of historical loan...+3 more